Concaten8 Data ServicesFernstone Law

Every piece of work needed to take a claim from first enquiry to submission to the Official Injury Claim service, when each is expected, and what each one is waiting for. Dates after today are CC8's forecast and are not yet agreed.

Done Built, in testing In progress Planned Waiting on others On the critical path Milestone

Waiting on other people

Each of these is outside CC8's control. The last column shows what it holds up, so the cost of a late answer is visible.

Later stages

Outline only. These are planned in detail once stage one is complete.

What changed

    How to read the chart

    • Lines run from a task to the tasks that cannot start until it is finished.
    • The critical path is the chain with no spare days. A day lost on any task in it moves the finish date.
    • Float is the number of working days a task can slip before it moves the finish date.
    • Built, in testing means it works in the development portal and is being tried by people, not that it is signed off.